London hub stands firm on proposed expansion after government oversight committee casts doubt on project, while airlines continue to push for a cheaper scheme.
A report by the UK House of Commons Transport Committee calling for expansion plans at London Heathrow to be “grounded for now” has not deterred the airport, as it battles against the latest in a long list of setbacks to its dream of adding a third runway.
The 26 November report on the draft Heathrow Expansion National Policy Statement (HENPS) calls for Heathrow’s expansion plans to be “grounded for now” and urges the government to “go back to the drawing board before proceeding any further”.
It criticises the lack of an overall strategy for aviation and calls for more work to establish the full range of benefits and costs.
“Expansion should not go ahead at any price, or at any cost to society or the environment,” says the report.
Its verdict has landed just as the long-running debate over whether to build a third runway at Heathrow seemed to be moving on.
After more than 20 years of argument, the project appeared closer than ever to getting off the ground following endorsement from UK chancellor John Healey, who reaffirmed government support on 11 November. However, prime minister Andy Burnham has never openly backed the project.
Airport executives, airlines and regulators had turned their attention from whether to build a third runway, to who should pay for it and how.
Table of Contents
What the committee found
The HENPS sets out four tests that expansion must meet, covering economic growth, climate, air quality and noise. The committee found shortcomings across all four.
On the economy, the report highlights Department for Transport (DfT) GDP modelling that represents a marked decrease from previous analyses and shows a “relatively modest” level of additional growth. While the government has positioned expansion as “critical” to national growth, the committee finds that “the case for this designation applying to Heathrow expansion has not been made”.
On climate, the report points to recent advice from the Climate Change Committee (CCC) that Heathrow expansion is not compatible with the UK’s carbon budgets or net zero target under current policies. That advice is “a clear signal that, at present, the government is failing that test”, the report says.
The committee also says the air quality and noise tests need strengthening, and highlights a lack of certainty over the cost of expansion, which could ultimately affect the prices paid by airlines and passengers. It also points to inadequate plans for surface public transport, such as new rail links into Heathrow from the west and south.
“Our report should be a wake-up call for ministers,” says committee chair Ruth Cadbury, whose constituency is near Heathrow. “We found that the government should have set out its overall strategy for aviation before publishing the draft HENPS. It did not do so and now it has failed to make the case for Heathrow expansion.”
She adds that the DfT “appears not to have given itself enough time to produce the most complete economic analysis”, and describes the CCC’s evidence as “a damning verdict on the climate impact of a third runway that government cannot overlook”.
The committee took more than 90 pieces of written evidence over five months and questioned community groups, the aviation sector, academics, local authorities, economists, the CCC, the promoters of both proposed runway schemes and the aviation minister.
Heathrow and government stand firm
Heathrow chief executive Thomas Woldbye says the airport remains committed to the third runway, arguing that “the overwhelming weight of evidence and support remains strongly behind Heathrow expansion” from unions, business, airlines and most MPs. The focus now, he says, should be on “delivering this privately financed project”.

The DfT says it will consider the committee’s findings as it reviews consultation responses, with Heathrow Reimagined, an airline-led coalition including IAG, Virgin Atlantic and American Airlines, saying it supports expansion “but not at any cost”.
Citing the report’s finding that economic regulation at Heathrow “could work harder”, the group is urging the UK Civil Aviation Authority (CAA) to move quickly on fundamental regulatory reform.
The $64 billion question
That cost uncertainty is already at the centre of the industry debate and featured heavily at the Airlines 2026 conference in London on 11 November.
The privately owned Heathrow Airport Limited puts the cost of expansion at £49 billion ($64 billion). It says £21 billion covers the runway and airfield, including moving the M25, and £12 billion goes towards new terminals and stands. The remaining roughly £15 billion modernises the existing airport – work Heathrow says it would do with or without a new runway.
British Airways parent IAG, the airport’s largest operator, says the plan is too expensive and is pitching several alternative funding models, including a government stake, a phased build and tax relief. IAG stresses that it supports expansion and that the decision rests with the government.
BA believes the project can be delivered for £19 billion less. “We can keep charges competitive,” chief executive Sean Doyle told Airlines 2026. That figure of £30 billion matches an affordability study by consultancy Oliver Wyman, published by the CAA in May 2026, which estimates the amount of capital airlines could absorb at up to £30 billion.
The difference matters because airlines pay for the airport through charges, which feed into fares. Doyle argues that raising per-passenger charges beyond the £28.66 cap could lock up more of the airlines’ own investment.
Charges are already rising. The CAA has allowed Heathrow to recover up to £320 million of early expansion costs from 2025 and 2026. Airlines for America chief executive Chris Sununu warns that unchecked costs could eventually price out “low-income customers”.
Several of IAG’s options would move part of the bill away from airport charges and onto the public purse, through tax reliefs, a share of air passenger duty or a government stake.
The phased option echoes a rival Heathrow West scheme from the Arora Group, a major landowner around the airport. In 2025 the government chose Heathrow’s 3,500m (11,483ft) runway, which crosses the M25 motorway, over Arora’s shorter design. Arora now proposes building the longer runway in two stages, starting with a runway of about 2,400m that stops short of the motorway.

Arora tells FlightGlobal that Phase 1 would cost £23 billion in total, including the runway and supporting infrastructure. Founder Surinder Arora told the Airlines 2026 conference that a first-phase runway of that length could handle more than 99% of narrowbody movements and a share of widebody operations. Narrowbodies make up about 60% of Heathrow’s traffic today, he says, and the runway could later be extended to full length without affecting operations.
The regulator and the airport
CAA chief executive Rob Bishton says early costs already “play right through” into what passengers pay, and that the regulator wants better capital governance and efficiency.
“We’ve reached the moment where the central presumption cannot be that the existing incumbent does all capacity expansion and asset investment without some questions being looked at,” he says. “There could be competition on design, build and operation,” he adds, though “nothing is resolved”.

Woldbye rejects the idea that expansion is a windfall for Heathrow’s shareholders. “I don’t think it is a pot of gold,” he says. “We are regulated by the CAA.” Investors should earn “a reasonable risk-adjusted return”, he says, stressing that “this is our investors’ money”. He concedes the industry has never properly discussed how to make the runway cheaper because, until recently, nobody knew whether it would go ahead.
Heathrow adds: “We’re going through the plans together, challenging costs and stripping out anything that doesn’t deliver value. Expansion must be affordable for airlines and passengers as well as financeable for investors, and we’re determined to deliver it.”
Why it matters
For airlines, the case for building at Heathrow rests on its hub status. “I would certainly no longer take that for granted,” Airlines for Europe managing director Ourania Georgoutsakou told the conference. “I think this is the alarm bell.”
Half the passengers on BA’s Cincinnati service connect beyond Heathrow onto its short-haul network or to Africa and the Middle East, Doyle says. Woldbye says the UK will not win its share of future demand from Africa and Asia “unless we build a third runway”.
Heathrow has operated at 99% capacity for more than a decade, bar the Covid-19 pandemic. Its terminals are full too: the airport is reshuffling carriers to use stranded space, moving Delta Air Lines from Terminal 3 to Terminal 4 in 2028 and splitting it from joint-venture partner Virgin Atlantic. Doyle calls it “another manifestation of the fact that we don’t have infrastructure fit for [the] future”.
The long road to consent
Parliamentary scrutiny of the draft HENPS ended on 26 November, and Heathrow’s consultation on its development consent order (DCO) will close on 22 December. The government is targeting a final planning decision in 2029.
Woldbye expects “one of the biggest and most complicated DCOs ever delivered in this country”. Asked where the industry will be in 10 years, he says it will be celebrating the opening of a third runway.
Whether it gets there now depends on two things: whether ministers can answer the committee’s challenge on growth and climate, and whether Heathrow, its airlines and the CAA can agree on who pays.